Retaining Wall Backfill: What to Use and How to Place It

Use clean, angular crushed stone directly behind the wall, in a zone at least 12 inches wide, and compact it in thin layers. Keep fine soil, clay and organic material out of that zone. Backfill does more than fill a hole. It drains water away from the wall, and water pressure is what pushes most retaining walls over. Below is what to put behind the wall, how to place it, how the footing or base fits in, and when the job needs an engineer.

Actionfenceanddeck
Build a Retaining Wall That Drains
Action Fence and Deck builds durable retaining walls with attention to detail, tailoring outdoor construction to your property’s needs.

Explore retaining wall services

TL;DR

  • Use free-draining, angular crushed stone (such as #57 or #78) directly behind the wall. Skip pea gravel, screenings, and clay.
  • Make the gravel zone at least 12 inches wide for segmental block walls, and add a drain pipe and outlet so water has somewhere to go.
  • Place and compact backfill in lifts of 8 inches or less. Use only a walk-behind plate compactor within 3 feet of the blocks.
  • Most block walls rest on a compacted stone base with the first course buried. Tall walls or walls holding a driveway or building need an engineer.
  • In the Fort Worth area, clay soil holds water and swells, which makes drainage stone and outlets non-negotiable.

Table of Contents

What material works best as retaining wall backfill

The best backfill is crushed, angular, open-graded stone with almost no fine particles. The Federal Highway Administration describes crushed open-graded aggregate as a structural backfill option because of its very low fines, free draining behavior, low frost-heave potential, easy placement and high strength. It also notes that angular stone is preferred over rounded stone where strength matters.

The Concrete Masonry & Hardscapes Association (CMHA) says gravel fill is free-draining aggregate suited to segmental retaining walls. Placed behind the wall units, it helps remove incidental groundwater and reduces hydrostatic pressure. It also acts as a filter that keeps retained soil from washing through the joints in the face. And it lets crews compact with lower forces, which is easier on the blocks.

For the stone itself, the USDA Natural Resources Conservation Service defines acceptable gravel fill as sand, gravel, crushed stone or mixtures from approved sources that exclude organic matter, clay balls, excessive fine particles and anything else that blocks free drainage. In plain terms: if you can squeeze it into a muddy ball, it does not belong in the drainage zone.

On a typical residential job, that means washed, angular crushed stone in the #57 or #78 size range, which are common sizes sold at Texas stone yards. Pea gravel and river rock are rounded and tend to shift, and screenings (the dusty fines left from crushing) hold water instead of passing it.

Angular stone, rounded gravel and dusty screenings

Gradation: what the specs actually say

You do not need to run sieve tests on a backyard wall, but it helps to know what the engineering guidance looks like, so you can ask your installer the right questions.

Guidance Typical requirement
Allan Block, wall rock directly behind facing Well-graded, compactable stone about 0.25 to 1.5 inches, with no more than 10% passing the No. 200 sieve
Allan Block, reinforced zone fill Select or structural fill with less than 10% fines
FHWA example for structural backfill (GRS walls) Maximum grain size 0.5 to 2 inches; no more than 12% passing the No. 200 sieve if well graded, or 5% if open graded

The common thread is low fines. Fines are the silt and clay-sized particles that clog drainage and hold water against the wall.

Can you use sand or the soil you dug out?

Sometimes, but not in the zone right behind the wall. Excavated soil is fine as the last fill farther back, as long as it contains no organic material, and the drainage zone of clean stone sits between it and the wall. Fort Worth’s heavy clay is the soil to be most careful with. Clay swells when wet and shrinks when dry, and it holds water. Packed directly against the wall, it loads the wall in a way a free-draining stone zone does not.

Sand drains, but it is not the same as clean crushed stone. Rounded sand grains do not lock together the way angular stone does. Sand also washes out through gaps in the face if there is no stone or fabric in front of it. Allan Block’s guidance on proper soils for a retaining wall recommends a well-graded, compatible aggregate for the base and drain field. It describes crushed stone as having high shear strength, good compaction, and excellent drainage and freeze/thaw resistance.

The soil conditions at your property, and the wall height, decide how much of the backfill needs to be stone. A short garden-bed wall can behave very differently from a 5-foot wall holding a driveway. A University of Nebraska extension publication on rock walls makes a related point: site and wall design should be considered individually, and using less rock is false economy.

Can you use sand or the soil you dug out?

The drainage zone, pipe and fabric

Backfill and drainage work as one system. A generic segmental-wall installation guide calls for a drainage aggregate zone of at least 12 inches, a sloped drain pipe of at least 4 inches, and outlets at the lowest point and at least every 50 feet. It also recommends filter fabric over the backfill and drainage stone, to limit the migration of fines.

CMHA is a little more cautious on one point. It recommends at least 12 inches of free-draining gravel fill directly behind the units, but says that zone is not automatically the main drainage path. The designer has to address site groundwater and provide a way to collect and evacuate it. CMHA gives a minimum pipe diameter of 3 inches, with the size and elevation depending on site conditions, and says outlets or weep holes should be no more than 50 feet apart.

Put together, a sound drainage build behind a block wall looks like this, from the wall back:

  1. Wall units with the first course buried on a compacted stone base.
  2. At least 12 inches of clean crushed stone directly behind the units.
  3. A perforated pipe at the base of the stone, sloped to a daylight outlet or a proper drain.
  4. Filter fabric separating the stone from the soil behind it.
  5. Compacted native or select soil beyond the fabric, capped with soil that sheds surface water away from the wall.

If you want to see how a four-part drainage approach for new builds and retrofits is laid out, that guide walks through it in detail. We cover the same ground in our own piece on retaining wall drainage and how to prevent failure.

How to place and compact backfill without damaging the wall

Backfilling is where a good wall often gets hurt. Too much compaction right behind the blocks pushes them forward, and too little leaves voids that settle.

Allan Block’s residential guide says to place and compact backfill in lifts of no more than 8 inches. It also says to use only walk-behind plate compaction equipment within 3 feet of the blocks and to keep heavy equipment at least 3 feet away. The reason is that heavy compaction close to the face can cause bulging or forward rotation. The generic installation guide cited above gives a slightly tighter range of 6 to 8 inches per lift.

A simple sequence works on most residential walls:

  1. Set and level each course, then fill the cores and the 12-inch zone behind with clean stone.
  2. Place the stone and the soil behind it in layers no thicker than 8 inches, and compact each before adding the next.
  3. Lay the drain pipe at the base and confirm that it slopes to its outlet before covering it.
  4. Keep skid steers, dump trucks and rollers well back from the face while the wall is fresh.
  5. Finish with a cap and grade the soil at the top so surface water runs away from the wall, not into it.

Walls that lean back slightly are more stable. The Nebraska publication recommends planning at least two to three inches of batter per foot of wall height for rock walls. Block systems build in their own setback per course, so follow the manufacturer’s numbers.

If you see the face bowing after a few seasons, check drainage first. Our guide on a bowing retaining wall explains what to measure and when it becomes urgent.

Footing and base depth

Most homeowners searching for backfill also ask whether the wall needs a footing. The answer depends on the wall type and height. Segmental block walls are generally built on a compacted crushed-stone leveling pad with the first course buried below grade, rather than on a poured concrete footing. Poured, mortared and taller masonry walls, and walls carrying heavy loads, are designed with reinforced concrete footings that the engineer sizes.

The depth and width are not one-size-fits-all. They depend on wall height, soil bearing capacity, what sits above the wall (a slope, a driveway, a fence or a structure), local frost depth and drainage. Fort Worth rarely sees deep frost, but its expansive clay can move a footing or base that is shallow or poorly drained. Your block manufacturer’s installation manual gives the buried-course and base-thickness figures for its system, and an engineer’s drawing overrides any rule of thumb.

Two practical points:

  • Dig the base trench wider than the block so the compacted stone extends in front of and behind the first course.
  • On a slope, step the base in level sections rather than following the grade.

If your wall will carry a fence, we have a separate checklist for a fence on a retaining wall. If the wall is tiered, see terraced retaining wall failures and drainage-first design.

Reinforcement, height limits and engineering

Taller block walls often need geogrid, a layer of reinforcing mesh that ties the wall into the soil behind it. The reinforced zone then needs structural fill with low fines. Read our guide to geogrid for retaining walls for how it works and when it is specified.

Permits and engineering vary by city, so check with your local building department before you dig. As an example of how cities write the rule, Herriman, Utah requires a permit for a wall with 4 feet or more of unbalanced fill, or a shorter wall that holds a surcharge. It requires engineering for any wall holding a surcharge, and its application asks for a site plan showing drainage flow and anything within the surcharge area. Rancho Palos Verdes, California measures wall height from the bottom of the footing to the top of the wall when it decides whether a permit is needed. Those are two examples, not the rules for Fort Worth, Dallas or your suburb. Confirm your own city’s threshold.

If the wall is near 4 feet, sits below a driveway, pool, slab or structure, or you are on a slope with a history of movement, bring in a professional. We explain the process in when you need an engineer for a retaining wall and how to hire one, and in our overview of the retaining wall height limit and permit question.

Our perspective on backfill

Most retaining walls we are called to repair did not fail because of the blocks. They failed because of what went behind them: native clay packed against the face, no outlet for the pipe, or a heavy compactor run right up to the wall.

After more than 20 years of building fences, decks, retaining walls and concrete work, our rule is simple. Spend the money on clean stone and a drainage path that works, because that is the part nobody sees once the wall is finished. We would rather quote a wall with a proper drainage zone and an honest budget than a cheaper one that needs to be rebuilt.

We also tailor each build to the site and to your budget. Soil, slope, what sits above the wall and where the water goes all change the design, and we talk through those choices with you in a free quote.

Abraham

Have us build or fix your wall

Backfill is heavy, repetitive work, and mistakes are expensive to dig out. If you would rather have licensed and insured builders handle the excavation, stone, drainage and compaction, we build retaining walls along with concrete, masonry, decks, fencing and landscaping in the Fort Worth and Dallas area.

Actionfenceanddeck

Request a free quote through our services page and we will look at the slope, the soil and the drainage before we recommend anything.

FAQ

What is the best gravel for retaining wall backfill?

Clean, angular crushed stone with no fines, such as #57 or #78, is the standard choice behind block walls. Angular stone locks together and drains freely. Pea gravel, river rock and screenings are poor choices for the drainage zone. Your wall manufacturer’s manual and any engineer’s drawing take priority.

How wide should the gravel zone behind a retaining wall be?

CMHA recommends at least 12 inches of free-draining gravel fill directly behind segmental retaining wall units. Taller or reinforced walls can need more, and the design decides how much. The zone should connect to a drain pipe and outlet.

Can I backfill a retaining wall with sand?

Sand drains, but it is not a substitute for clean crushed stone directly behind the wall. It can wash through gaps in the face without stone or fabric in front of it. Use stone in the drainage zone and keep sand or native soil farther back, if your design allows it.

Do retaining walls need footings?

Segmental block walls usually sit on a compacted stone base with a buried first course, while poured or mortared walls and heavier loads call for engineered concrete footings. The wall height, soil, drainage and what sits above it all matter. Check your block manufacturer’s manual and your city’s requirements.